Hartek Power commissions 66/11-KV substation in record time

Hartek Power commissions 66/11-KV substation in record time

Chandigarh, September 11, 2015: Hartek Power, one of India’s fastest growing Engineering, Procurement and Construction (EPC) companies based in Chandigarh with expertise in executing high-voltage turnkey substations and power infrastructure projects, has once again demonstrated its expertise by commissioning a 66/11-KV substation on complete EPC basis at Lovely Professional University, Jalandhar in a record period of 78 days.



Going by industry standards, it usually takes four-five months to complete a 66/11-KV substation. Hartek Power has set a new benchmark by commissioning this project in nearly half the time.



Hartek Power is also expected to soon commission a 132/11-KV substation and transmission line project in Madhya Pradesh, which it had bagged from Amba Shakti on complete EPC basis.



Attributing the achievement to the company’s commitment towards quality and timely delivery, Hartek Power Chairman and Managing Director (CMD) Hartek Singh said, “We specialise in fast-track execution without compromising on quality, our core value that is reflected in all the projects we have undertaken. Having set our eyes on completing the LPU substation project before the commencement of the new academic session, we left nothing to chance. Known for our reliability and professional acumen, we share a strong bond with leading capital power equipment manufacturers across India.”



Credited with executing more than 130 substations in the past seven years, Hartek Power has handled substation projects in 17 states across the country. It has been entrusted by various state electricity boards with substation projects worth Rs 60 crore, which are likely to be commissioned in this financial year. The company is also holding final-stage talks for executing substations for 200-MW solar projects in the country in the current financial year.





About Hartek Power

Hartek Power Pvt Ltd is one of India’s fastest growing Engineering, Procurement and Construction (EPC) companies with expertise in executing high-voltage substation turnkey and rooftop solar projects and manufacturing a complete range of power distribution equipment/solutions catering to the needs of the industry as well as utilities. The company, part of the billion-INR Hartek group, operates through four strategic business units—Power Systems, Rooftop Solar, Power Distribution Products and Fuel Services.



Having a long-standing tie-up with reputed global suppliers like Siemens and Schneider Electric, Hartek Power has secured more than 3,000 clients and 120 projects since its inception about 25 years ago. Held in high esteem for its timely execution of projects, the Chandigarh-based company, which recorded a revenue of Rs 125 crore in FY 2014-15, provides complete EPC solutions on substations and transmission lines to the industry, independent power producers (IPPs) and utilities. An emerging player in the renewable energy sector, the company also provides complete EPC, turnkey and rooftop solar installation solutions. Formerly known as Amtek Energy & Power Pvt Ltd, Hartek Power (www.hartekpower.com) has a complete range of high-voltage and low-voltage equipment required by the industry and utilities for transmission and distribution.

The firm also manufactures various power distribution products in partnership with global energy giant Schneider Electric and acts as a distributor of Reliance furnace oil. It is the third largest facilitator in the country in the area of fuel services.

NEWS ID : 700 | 11 Sep 2015 | By : Reporter
Other NEWS :
Shere This News On :
facebook twitter google+ share email delicious reddit digg stumbleupon
Comments

No Access (Please Login To Comment)

Show my ad here
Show my ad here
© 2024 gsnews.in